Quarterly Screenings Process

Overview

Quarterly Screening Process, as viewed at a high level, which is performed by Assessors.

Quarterly Screenings are done every three months and do not require a site visit. However, an Assessor may schedule the quarterly screening to coincide with an annual monitoring. (per Texas Rising Star Staff Handbook)

Team

Centralized Assessment Entity Assessors

Team members

Centralized Assessment Entity Assessors

Team mission

Provide consistent and reliable screenings of Texas Early Learning Program meeting the standards for the Texas Rising Star program certifications and star levels

Process Flow Diagram

Process Flow Chart

Role Performing Task

Process Task Number

Task

Input for Task

From

Output for Task

To

Media or Application

Assessor

1

Assessor Assignment/ Update

New Jira Screening Ticket, Assessor assignments and availability

Assessor Assignment query

Assessor Assigned, Jira ticket status update

Assessor

Jira ticket

Assessor

2

Monitor Deficiencies

CCR Auto-updates

TWC

Screening Results, Jira Ticket status update

NA

Engage/ Jira Ticket

Assessor

3

Criteria Met?

Screening Results

Assessor Screening

Determination if Criteria is Met

NA

Engage

Assessor

4

If :No

Deficiencies Identified

Assessor Screening

Auto-Generated Event Log

Assessor

Engage

Auto-Generated Event Log and go to step 6

Assessor

5

If Yes:

Required and supporting documentation upload

Assessor

No Deficiencies Identified, Jira Ticket status update

Assessor

Engage/ Jira Ticket

Go to step 21

Assessor

6

Was there an Impact?

Screening Results

Assessor

Determine if Impact occurred

Assessor

Engage

Assessor

7

If No:

Screening Results

Assessor

Jira Ticket Status update

Assessor

Engage/ Jira

Event Log created and go to step 21

Assessor

8

If Yes:

Screening Results

Assessor

Determine Type of Impact

Assessor

Engage 

Identify Type of Impact based on Findings
Probabtion, Star Level Drop or SIA gp to step 9
Suspension go to step 14

Assessor

9

Event Log Creation (TRS Probation Event, Star Level Change, SIA)

Screening Results

Assessor

Event Log Created, Jira Ticket Status update

Assessor

Engage/ Jira

Assessor

10

Impact Notification (includes form completion)

Screening Results

Assessor

Completed Impact Notification and Form, Jira Ticket Status update

ELP, Assessor, LWB, Mentor

Engage/ Email/ Jira 

Assessor

11

Impact Ended?

 

Assessor

Screening Criteria

Assessor

Engage

Assessor

12

If Yes: CCR Screening 

CCR Auto-updates

TWC

Screening Results, Jira Ticket status update

NA

Engage/ Jira Ticket

Assessor

2

If No:

Jira trigger or reminder of Impact Period

Assessor

Screening Results and Jira Ticket Status update

Assessor

Engage/ Jira Ticket

 Go to step 2 Monitor Deficiencies at next time period

Assessor

13

Criteria Met?
If Yes: Go to step 13A
If No: Go to step 4

Screening Results

Assessor Screening

Determination if Criteria is Met

NA

Engage

Assessor

13A

 End of Probation or Star Level Drop Period
Go to step 21

Screening Results

Assessor

Probation lifted or Star Level Reinstated, Jira Ticket Status update 

Assessor

Engage/ Jira

Assessor

14

If Suspension:

Screening Results

Assessor

Event Log created, Jira Ticket Status update

Assessor

Engage/ Jira

Event Log Creation (Suspension Type)

Assessor

15

Impact Notification (Includes form completion)

Screening Results

Assessor

Completed Impact Notification and Form, Jira Ticket Status update

ELP, Assessor, LWB, Mentor

Engage/ Email/ Jira

Assessor

16

Review ELD Points Threshold Monthly

ELD Points Threshold

Assessor

ELD Points Threshold Calculated

Assessor

Engage

Assessor

17

Notify LWB of Threshold Monthly

ELD Points Threshold Calculated

Assessor

Notification of the ELD Points Threshold Monthly

HGAC

Email/ Report

Assessor

18

Create Event Log tracking ELD Points Threshold Monthly

ELD Points Threshold Calculated

Assessor

ELD Points Threshold Calculated

Engage

Engage

Assessor

19

Determine if ELD Point Threshold was Met

ELD Points Threshold Calculated

Assessor

Determine if ELD Point Threshold was or was not met

Assessor

Engage

Assessor

20

If Yes for step 19:

Impact End Date: Impact Ended

Assessor

Identification of Impact End date, Jira ticket status update

Assessor

Engage/ Jira

Identify if Impact (Suspension) is ended; If No go to step 16

Assessor

21

If Yes for step 20::

Impact Ended

Assessor

Email Notification; Jira Ticket Status update

LWB/ Mentor

Email

Notify LWB

Assessor

22

If No for step

ELD Threshold Point Met Determination - Not Met

Assessor

CCS Agreement Ended and Notification to Payment office; Jira Ticket Status closed

Payment office

Email

CCS Agreement Ended Notification (Notify the Payment office of the CCS agreement

LFM

23

Fidelity Monitoring

Jira Ticket data

Assessor

Fidelity data

Stakeholders

Email/ Report

LFM

24

Close of Process

 

 

 

 

 

Roles and Responsibilities

R-Responsible, A - Accountable, C - Consulted, I - Informed (Directly or by Report)

The RACI chart is a type of responsibility assignment matrix which lists all stakeholders and the level of involvement in each task, denoted with the letters, R, A, C, or I.

Responsible (R) roles: designates the task as assigned directly to this role. This is the person who does the work to complete the task or create the deliverable. Must have one and could have several Responsible roles.

Accountable (A) roles: delegates and reviews the work involved, This person makes sure the responsible person/role knows the expectations of the task and completes the work on time. Only one person/role is accountable.

Consulted (C) roles: provide input and feedback on the work being done. This person/ role has a stake in the outcome of the task as it could affect their current or future work. Not a required responsibility for a task.

Informed (I) roles: need to be looped in the progress of the task, but not consulted or overwhelmed with the details. The task could affect their work, but they are not decision makers for the task. Usually outside the and are not a required responsibility for the task.

 

 

 